Brookings County-Hampton 345 kV
project
The Brookings County-Hampton transmission line will
improve reliability throughout southwest and west
central Minnesota and the Twin Cities as well as
enable access to new generation, including renewable
energy resources in the area. The new line will be
constructed from a new substation in Brookings County,
South Dakota, to a new substation in Hampton, Minnesota.
The Minnesota Public Utilities Commission (MN PUC)
approved the Route Permit application for the majority
of the Brookings County-Hampton transmission line
on July 15, 2010. The approved route follows the
modified preferred route as identified in the original
application and subsequent testimony, as modified
by an approximate two-mile route segment in Dakota
County (segment P6-06 was proposed in the Environmental
Impact Statement scoping process).
The MN PUC has not yet approved the segment between
the Cedar Mountain substation in Renville County
and the Helena substation in Scott County, as it
referred the Minnesota River crossing location back
to the administrative law judge (ALJ). The ALJ will
consider a June 2010 letter from the United States
Fish and Wildlife Service regarding impacts to eagles
at the river. To further develop the record regarding
the crossing, the MN PUC will host public meetings
October 4-6 in Belle Plaine, Arlington and Le Sueur.
Exact times and locations are still being finalized.
The segment between the Lyon County and Helena substations
will be constructed as a double circuit transmission
line. The other segments will be constructed with
double circuit capable structures; only a single
circuit will be energized after initial construction.
Single pole steel structures will be used to reduce
land impacts. Structures are between 140 and 170
feet tall and will be between 800 and 1,000 feet
apart. Typically, a 150-foot right-of-way will be
required.
Minnesota permitting
The MN PUC must grant two approvals
before construction – a
Certificate of Need and a Route Permit. An environmental
report was prepared by the Department of Commerce,
Office of Energy Security during the need process,
and an Environmental Impact Statement was written
during routing.
South Dakota
permitting
The South Dakota Public Utilities
Commission must issue a Facility Permit before transmission
line construction.
- Late
2010 (anticipated) – filing
of Facility Permit application
- Route option map
|