July 13, 2009 – CapX2020 is in the early phases
of execution to design, engineer and construct nearly
700 miles of 345 and 230 kilovolt transmission lines,
including the modification and new construction of more
than 15 substations. The resourcing effort, as part
of the CapX2020 Project Management Office (PMO), is
currently developing procurement plans, which will be
used to facilitate the development of RFPs and requests
for quotes (RFQs) for each of the major service and
material categories. The PMO expects to begin issuing
requests for proposals (RFPs) during the third quarter
of 2009, with sourcing activity remaining heavy throughout
2010. These early activities are intended to keep the
projects in a position to meet the published in-service
dates. Construction start dates and financial commitments
remain contingent on formal granting of each project’s
route permit.
The CapX2020 PMO is dedicated to providing regular
communication to ensure interested parties are up-to-date
with the latest information regarding project participation
opportunities. Please check back for future updates.
Suppliers who haven’t already contacted the CapX2020
PMO and would like to be considered for the four CapX2020
Group 1 Projects can email a short description or statement
of qualifications of their firm’s services with
contact information to: CapX2020PMO@xcelenergy.com.